Retail Center Slab Crack Repair

This large retail center was experiencing severe cracking in multiple areas. The contractor installed approximately 1,000 Crack Stitches as part of the overall space remodel. As the images show, stitches were installed roughly 12″ apart, perpendicular to the crack to maximize the tensile strength of the carbon fiber and prevent future crack expansion. The cracks were filled with the same Xtreme 4070 epoxy used for the installation of the crack stitches.